RECENTLY COMPLETED PROJECT

340 Haven Avenue, 10033 NYC

Apt Remodel & Painting – Total Price $25,000

PROJECT INFO

COMPLETION TIME

0
DAYS

Great job Frank. I am so happy with my new bathroom and the lighting in the living room. 

340 HAVEN AVENUE - OWNER

BEFORE & AFTER PICTURES

BEFORE PIC OF BATHROOM AT 340 HAVEN AVEAFTER PIC OF BATHROOM AT 340 HAVEN AVE
BEFORE PIC 340 HAVEN AVENUEAFTER PIC 340 HAVEN AVENUE
BEFORE 340 HAVEN AVENUE - BATHROOMAFTER 340 HAVEN AVENUE - BATHROOM

BATHROOM REMODEL

  • Installation of 47 Square Feet of Black & White Porcelain Matte Floor Tile
  • Installation of 135 Square Feet of Ceramic Bright White Wall Tile including the window

  • Installation of new Brushed Gold shower system with rain shower head
  • Installation of new walls and new ceiling and new ceiling crown molding
  • Installation of new wall mounted Brushed Gold vanity light
  • Installation of new dual flush standard toilet

  • Installation of new towel rod, toilet holder, curtain rod, towel hook all in Brushed Gold
  • Installation of new Brushed Gold vanity sink faucet and drain

  • Prime and Painting of walls and ceiling (2 Colors)

  • Glazing of bathtub

  • Installation of new dual GFCI light switch & receptacle outlet

ELECTRICALS & FIXTURES

  • Installation of new electrical wiring at ceiling in living room
  • Installation of six (6) recessed six inch light fixtures at living room ceiling
  • Installation of new electrical wiring throughout the foyer, kitchen and closets

  • New wiring and installation of new recessed lighting at foyer area
  • Installation of Brushed Gold Sputnik pendant light at dining area

  • Installation of new Harbor Breeze ceiling fan with wall switch at bedroom

  • Installation of new wiring for new switches for all lighting and fixtures

  • Installation of new receptacle outlets
  • Repair of receptacle outlets

  • New wiring and new installation of two (2) recessed six inch light fixtures in closets
  • Installation of new white RG6 coaxial cable for television and modem 

APT REMODEL

  • Removal of existing baseboards throughout entire apartment

  • Installation, priming and painting of 5 1/2 inch hardwood baseboards
  • Installation, priming and painting of quarter round base molding
  • Installation, priming and painting of 4″ ceiling crown molding

  • Refinishing all door frames and window frames
  • Compounding and sanding of walls surrounding window frames

  • Minor patching and wall repair throughout apartment

  • Priming of all walls and ceiling

  • Painting of entire apartment, including door frames, closets, trim, moldings, doors, ceilings, walls and window frames

PROJECT CHALLENGES

  • With the apartment vacant, there were little to no challenges other than the normal renovation challenges
  • The original scope of work had a 4 week timeline and 5 change orders requested by the client only extended the project completion date by five days.
  • The client was really helpful, had a gift for apartment design, and provided the project manager with ample time to purchase the materials for the change orders.
  • To change and install the new shower system and toilet lines, the building had to shut down the water to the entire building. Thanks to our plumbing experts, the water shutdown lasted only 10 minutes.